Transactional Reporting

Firm Service Contracts

Click here to download.

Date PostedShipper Legal NameIdentification NumberContract NumberRate ChargedMax RateEffective DateExpiration Date (subject to rollover)Receipt PointDelivery PointContract MDQSpecial DetailsNegociated Rate (y/n)Affiliate Relationship (y/n)Pipeline Seller (y/n)
2/3/2012The Cooperative District for Northeast Alabama Gas63-6002284CDNAG001$4.56/Dth per Month$5.4993/Dth per Month2/6/20122/6/2027ETNG#03CDNAG4200Yes. Please see note belowYNY
2/3/2012United States Gypsum Company00-5212600USGC001$5.4993/Dth per Month$5.4993/Dth per Month2/6/20122/6/2015ETNG#02USGC5000 NYY

Special Details

Service to commence the later of (a) November 15, 2011 or (b) completion of Transporter’s delivery point facilities and Shipper’s satisfaction of tariff requirements for creditworthiness. The Parties agree to a negotiated rate which will be fixed for the term of the FT Agreement at the following levels:

  1. Monthly reservation charge equal to $4.56/Dth, subject to the following increases (effective beginning the first month after the operating change occurs): (x) by $0.90/Dth if USGPC is required to implement an interactive electronic bulletin board or equivalent system for nominations, scheduling or other communications, (y) by $0.90/Dth if USGPC is required to implement separation of function rules limiting its flexibility to utilize USGC personnel to operate its pipeline, and (z) by $0.90/Dth if USGPC is required to construct and operate gas quality measurement facilities rather than rely on gas quality measurements posted by East Tennessee. For purposes of this provision, a change shall be deemed required if it was brought about by a FERC regulation or ruling which was not unilaterally sought by USGPC or attributable to an election by USGPC to sell gas delivered on its facilities other than in connection with cashouts or balancing.
  2. Commodity charges, surcharges and fuel/loss retainage to the extent provided by USGPC's tariff.
  3. An authorized overrun rate of $0.1833/Dth.
  4. CDNAG's rate will not be adjusted for credits that would reduce any of the foregoing.

Interruptible Service Contracts

Click here to download.

Date PostedShipper Legal NameIdentification NumberContract NumberRate ChargedMax RateEffective DateExpiration Date (subject to rollover)Receipt PointDelivery PointContract MDQSpecial DetailsAffiliate Relationship (y/n)Pipeline Seller (y/n)
2/3/2012The Cooperative District for Northeast Alabama Gas63-6002284CDNAG002$0.1833/Dth$0.1833/Dth1/5/2012EvergreenETNG#03CDNAG7200 NY
2/3/2012United States Gypsum Company00-5212600USGC002$0.1833/Dth$0.1833/Dth2/1/2012EvergreenETNG#02USGC5000 NY